Site supervision checklist for house construction: stage-wise checks

Long-span steel roof trusses over the New Town hall during construction
A long-span steel roof on site at the New Town banquet hall, during construction. On site: Banquet hall, New Town, Kolkata, by the studio.

The short answer

Site supervision means checking, at fixed stages, that the building is made as drawn and specified. IS 456:2000 sets minimum curing at seven days for ordinary Portland cement and a sampling rule of one cube set per 5 cubic metres of concrete. In West Bengal the architect or LBS and the structural engineer carry duties on site.

Site supervision is the checking, at fixed stages, that a building is being made as drawn and specified. The clearest numbers come from IS 456:2000: concrete is cured for at least seven days with ordinary Portland cement, and one set of cubes is taken for every 5 cubic metres or less. This checklist applies them stage by stage.

What is site supervision, and who is responsible for it?

Site supervision is a check on the work by someone who is not the contractor. It compares what is built with the drawings, the specification and the sanctioned plan, and it stops mistakes before they are buried under the next layer.

Facade of the New Town banquet hall under construction, with FRP panels and scaffolding
A facade under construction: the stage-by-stage checks in this guide happen on a site like this. On site: Banquet hall, New Town, Kolkata, by the studio.

In West Bengal’s municipalities, the 2007 rules put the duty on named people. Under rule 16 an architect or Licensed Building Surveyor is held responsible for any work executed on site in contravention of the rules, and is deemed to continue supervising unless a written notice of ceasing is given. Under rule 17 the structural engineer is responsible for full quality control of materials and workmanship, and for tests on materials by recognised institutions. No completion certificate is issued unless the test reports are submitted with the structural stability certificate. These are rules as gazetted in 2007, so check the amended text.

Government procurement guidance says the same in general terms: the Manual for Procurement of Works (June 2022) states that the quality of project works significantly depends on supervision and monitoring. The post on architect vs civil engineer vs contractor explains who does what.

What should be checked before work starts?

Before the first excavation, confirm the paperwork and the drawings.

  1. The sanctioned plan and the structural drawings, both signed, and one set kept on site. Rule 20 of the 2007 rules requires a copy of the sanctioned plan on site at all times.
  2. The soil investigation report and the foundation type it recommends.
  3. A written specification: cement grade, steel grade, brick or block type and tile specification.
  4. The authority’s commencement notice, where it applies. In New Town, rule 12 of the NKDA Rules requires a notice at least seven days before work begins.
  5. The stage payment schedule and the list of hold points in the contract.

A hold point is a stage after which the work is covered and cannot be checked again, so the contractor waits for sign-off before continuing.

What should be checked at foundation stage?

Foundations decide whether the rest of the building stays level and sound, so check them closely.

  1. Excavation depth and width match the drawing, and the base is clean and firm.
  2. Soil conditions match the soil report. Differences go back to the structural and geotechnical engineers before concrete is poured.
  3. Groundwater is controlled. InfraLens notes that Kolkata’s water table is often one to three metres below ground, so dewatering may be needed during excavation.
  4. For piles, records of depth, diameter and concrete placed are kept for each pile. Under rule 18 of the 2007 rules the geotechnical engineer certifies that the foundation was built as recommended, with the notice of completion up to plinth level.
  5. Cover to footing steel is 50 mm, which is the minimum IS 456:2000 sets for footings in clause 26.4.2.2.

What should be checked on reinforcement?

Reinforcement is checked before every pour, because concrete hides it.

  1. Bar diameter, number, spacing and lap length match the structural drawing.
  2. Bars are free of loose rust, oil and mud.
  3. Cover blocks or spacers are in place. IS 456:2000 says spacers and chairs should be at a maximum spacing of 1 m, and be of concrete of the same strength or PVC. For mild exposure the nominal cover in Table 16 is 20 mm.
  4. Column starter bars, beam-column joints, slab bottom and top steel, and sunk slabs for bathrooms are checked against the drawing.
  5. The structural engineer’s sign-off is obtained for slabs and beams before shuttering is closed.

What should be checked on shuttering?

Shuttering holds the wet concrete, so it must be rigid, tight and to line.

  1. Dimensions, levels and plumb match the drawing. IS 456:2000 requires formwork to remain sufficiently rigid during placing and compaction, and to prevent loss of slurry.
  2. Joints are tight, and the inside is cleaned of shavings, sawdust and binding wire.
  3. Props are vertical, braced and bear on firm ground or sole plates.
  4. Opening boxes, sleeves and conduits are fixed before the pour.

What should be checked during concreting?

The pour is a single event, so a supervisor should be present for it.

Black and white photograph of a cantilevered stair under construction at New Alipore
A cantilevered stair under construction at The Opulence: structure like this is checked at each stage before it is covered. On site: The Opulence, New Alipore, Kolkata, by the studio.
  1. The mix and the supply: grade, slump and source are as specified. For ready-mixed concrete, the delivery note is kept.
  2. Free fall is limited. IS 456:2000, clause 13.2, gives 1.5 m as the maximum permissible free fall as general guidance.
  3. Compaction is by mechanical vibrators, avoiding both under- and over-vibration (clause 13.3.1).
  4. Cubes are cast. Clause 15.2.2 sets the minimum sampling.
Quantity of concrete in the work Number of samples
1 to 5 cubic metres 1
6 to 15 cubic metres 2
16 to 30 cubic metres 3
31 to 50 cubic metres 4
51 cubic metres and above 4, plus 1 for each additional 50 cubic metres or part

At least one sample is taken from each shift. Cube results are kept with the structural engineer’s file, and rule 17 of the municipal rules makes material test reports a condition of the completion certificate.

How long should curing last and when can shuttering come off?

Curing keeps the concrete moist while it gains strength. Clause 13.5.1 of IS 456:2000 says exposed surfaces are kept constantly wet for at least seven days from placing where ordinary Portland cement is used, and at least 10 days where mineral admixtures or blended cements are used. The period is not less than 10 days in dry and hot weather.

The stripping times in clause 11.3.1 apply to ordinary Portland cement where the temperature stays above 15°C and curing is adequate:

Formwork Minimum period before striking
Vertical formwork to columns, walls and beams 16 to 24 hours
Soffit formwork to slabs (props refixed immediately) 3 days
Soffit formwork to beams (props refixed immediately) 7 days
Props to slabs spanning up to 4.5 m 7 days
Props to slabs spanning over 4.5 m 14 days
Props to beams spanning up to 6 m 14 days
Props to beams spanning over 6 m 21 days

The code says these periods may be modified for other cements and lower temperatures. If the specification names a different cement, ask the structural engineer for the stripping schedule in writing.

What should be checked on masonry, plaster and waterproofing?

These stages are finished surfaces on top of the structure, and their faults appear in the monsoon.

  1. Masonry: line, level and plumb, joints filled, openings sized to the door and window schedule, and lintels and sunshade bearings as drawn.
  2. Plaster: surfaces cleaned and wetted before application, thickness even, and plaster kept moist after it is applied.
  3. Waterproofing: terrace, bathrooms and balconies are tested with water before finishes go over them. The specification should set the product, the method and the test period, so the check has a standard to meet.
  4. Services: drainage and water supply lines are pressure-tested before they are closed in.

Seepage is a recurring Kolkata problem, and the post on damp and seepage in monsoon Kolkata explains how design decisions reduce it.

What do supervision charges look like?

Supervision is paid for within the architect’s fee or separately, depending on the appointment. In the published reproduction of the CoA scale, verification and certification of the contractor’s bills is listed at 1% in addition to the main fee, and advisory consultancy is listed at ₹4,000 a day for a local project and ₹10,000 a day outstation, accessed 13 November 2026. In the schedule of payment, 45% of the fee is due by the working drawings and tender documents, so the remaining 55% is spread across contractor appointment, construction stages and completion. The fee basis is in the post on architect fees in Kolkata.

What records should be kept?

Keep a site file with these items:

  1. Dated photographs at every hold point.
  2. A pour register with the date, element, grade, quantity and cube references.
  3. Cube test reports and steel test reports.
  4. Measurement sheets used to certify the contractor’s bills, which the post on the bill of quantities and contractor selection explains.
  5. Instructions given to the contractor, in writing.

What to do next

If you want site stages checked on a house under construction, the studio’s site supervision and project management page describes how that work is organised, and you can send the project details through the contact page.

Questions people ask

What is site supervision in construction?

It is the checking of work on site against the drawings, specification and sanctioned plan, at stages where errors are cheap to fix. It covers materials, workmanship, measurement and records, and it is separate from the contractor's own site management.

How often should the architect visit a house under construction?

Visit frequency is set in the appointment. A common arrangement is a visit at each hold point, such as footing, reinforcement before every slab, shuttering before each pour, and plaster and waterproofing before finishes.

What are the construction supervision charges in Kolkata?

There is no single rate. In the CoA scale as reproduced, site stages sit inside the percentage fee and verification of the contractor's bills is listed at 1% in addition. Advisory visits are listed at ₹4,000 a day locally. Confirm the current scale.

How long should concrete be cured under IS 456?

IS 456:2000 clause 13.5.1 says exposed concrete surfaces are kept constantly wet for at least seven days from placing where ordinary Portland cement is used, and at least 10 days with mineral admixtures or blended cements, or in dry and hot weather.

When can slab shuttering be removed?

For ordinary Portland cement in normal temperature, IS 456:2000 clause 11.3.1 gives 16 to 24 hours for vertical formwork, 3 days for slab soffit with props refixed, and 7 days for props to slabs spanning up to 4.5 m.

Who is responsible for quality control at site under West Bengal rules?

Under the 2007 municipal rules, the structural engineer is responsible for full quality control of materials and workmanship and for tests on materials, and the architect or LBS is responsible for work executed in contravention of the rules.

Sources

  1. IS 456: 2000 Plain and Reinforced Concrete, Code of Practice, Bureau of Indian Standards (public copy on law.resource.org). Accessed 2026-11-13.
  2. The West Bengal Municipal (Building) Rules, 2007, Government of West Bengal (Kolkata Gazette, 14 February 2007). Accessed 2026-11-13.
  3. CoA scale of charges (reproduction of the Council's scale), An Architect Explains. Accessed 2026-11-13.
  4. CoA schedule of payment (reproduction), An Architect Explains. Accessed 2026-11-13.
  5. House Construction Cost in Kolkata 2026, InfraLens. Accessed 2026-11-13.
  6. Manual for Procurement of Works (updated June 2022), Ministry of Finance, Department of Expenditure, Government of India. Accessed 2026-11-13.

Rules, fees and costs change. Figures are as published on the dates shown; check the current circular with the authority before you rely on them. This page is general information, not legal or financial advice.

Read next

  • Architect fees in Kolkata in 2026: percentage, per sq ft and scope

    Architect fees are a percentage of the cost of the works. The Council of Architecture scale lists 7.5% for an individual house, which is about ₹150 to ₹203 per sq ft at 2026 Kolkata build rates of ₹1,995 to ₹2,706. About 45% of the fee falls due by the tender-document stage.

    Guides,
  • Architect vs civil engineer vs contractor: who do you need for a house?

    An architect plans and designs the building, a structural engineer designs the frame, and a contractor builds it. In West Bengal municipalities the rules require a technical person of at least Licensed Building Surveyor rank for houses below 11.5 m, and a structural engineer above that. A contractor alone cannot sign the plan.

    Guides,
  • BOQ for house construction: format, rate analysis and comparing quotes

    A bill of quantities (BOQ) is a priced list of every item of work with its unit, quantity, rate and amount, so each contractor quotes the same scope. The Government of India's works manual pays item rate contracts on measured quantity, usually within 15% of the BOQ quantity per item.

    Guides,
  • Building a house in Kolkata while living abroad: POA, approvals, payments

    An NRI or OCI may buy non-agricultural property in India under RBI's Master Direction, and may be represented by an attorney under a power of attorney executed before a notary, magistrate or Indian consul and then stamped in West Bengal. Building authorities accept an authorised representative as applicant. Pay by stage against measured work.