3 cottah house plan in Kolkata: what G+2 and G+3 can you build?

Dream Villa banquet hall at Muchipara, four floors on a small city plot
Dream Villa stands on a plot of 1,138 sq ft, about 1.6 cottah, and rises to G+3. Photograph: Dream Villa, Muchipara, Kolkata, by the studio.

The short answer

One cottah is about 720 sq ft, so a 3 cottah plot is about 2,160 sq ft. Under the WB Municipal (Building) Rules, 2007, ground coverage is 65% up to 200 sq m, so a G+2 house can reach about 4,200 sq ft. KMC and NKDA apply their own rules, so the road width and the authority decide.

One cottah is about 720 sq ft, so a 3 cottah plot is about 2,160 sq ft. Under the West Bengal Municipal (Building) Rules, 2007, ground coverage is 65% up to 200 sq m, so a G+2 house can reach about 4,200 sq ft. KMC and NKDA apply their own rules, and the road in front sets the height.

How many square feet is a cottah, and what is a katha?

A cottah is a land unit used in Kolkata and across West Bengal, and one cottah is about 720 sq ft. A katha in West Bengal is the same unit. Katha is also used in other states, and the size differs from state to state, so check the unit written in the deed.

Plot Area in sq ft Area in sq m
1.5 cottah (katha) 1,080 100.3
2 cottah 1,440 133.8
3 cottah 2,160 200.7
4 cottah 2,880 267.6
5 cottah 3,600 334.4

The studio’s Dream Villa banquet hall at Muchipara stands on a plot of 1,138 sq ft, which is about 1.6 cottah. The studio’s Ballygunge Place residence is on 1,441 sq ft, which is almost exactly 2 cottah.

What rules decide what you can build?

Four things decide it: ground coverage, height, open spaces and, where a floor area ratio applies, the FAR. Each is set by the authority for the area.

  • Ground coverage is the share of the plot covered by the building at ground level.
  • Floor area ratio (FAR) is the total covered area on all floors divided by the plot area.
  • Open spaces are the setbacks at the front, rear and sides.
  • Height depends on the width of the road the plot faces.

Different bodies publish different tables. KMC applies the KMC Building Rules, 2009, where the permitted floor area depends on the width of the road, and you should read its table for your road. NKDA applies its own 2009 Rules. Other municipalities apply the West Bengal Municipal (Building) Rules, 2007, which the numbers below come from. These are rules as gazetted in 2007 and amended since, so confirm with the authority.

How much ground coverage do small plots get?

Under rule 46 of the 2007 rules, a residential plot up to 200 sq m gets 65% coverage and a plot above 500 sq m gets 50%. Between 201 and 500 sq m the percentage is found by direct interpolation. Applying that to cottah sizes gives:

Plot Plot in sq m Ground coverage Ground-floor footprint
2 cottah 133.8 65% about 936 sq ft
3 cottah 200.7 about 65% about 1,404 sq ft
4 cottah 267.6 about 61.6% about 1,775 sq ft
5 cottah 334.4 about 58.3% about 2,099 sq ft

The interpolation is arithmetic on the rule’s two end values. In New Town the NKDA Rules, in sub-rule (7)A of rule 22, give 65% for residential plots up to 3 cottah or 200 sq m, and Table IV gives 55% for residential plots below 1,500 sq m.

What height can I build to, by road width?

The 2007 rules tie height to the width of the means of access in rule 49. The figures exclude items such as a stair cover up to 2.4 m high and a parapet up to 1.5 m.

Width of road or passage Maximum height Roughly
2.40 to 3.50 m 8 m G+1
Above 3.50 to 7.00 m 11 m G+2
Above 7.00 to 10.00 m 14.5 m G+3
Above 10.00 to 15.00 m 18 m G+4 or G+5

The last column assumes about 3 m per floor, which is an assumption for this post, not a rule. For New Town, Table III of the NKDA Rules gives a maximum height of 15.1 m where the road is up to 10 m wide. On a narrow lane the lane sets the height, however large the plot is.

What are the setbacks for a G+2 or G+3 house?

Rule 50 of the 2007 rules sets minimum open spaces for residential buildings by height:

Double-height terrace with a chequered floor in the New Alipore apartment building
The double-height terrace at The Opulence, on a plot of 3,226 sq ft (about 4.5 cottah). Photograph: The Opulence, New Alipore, Kolkata, by the studio.
Building height Front Side 1 Side 2 Rear
Up to 8 m 1.2 m 1.2 m 1.2 m 2.0 m
Above 8 m and up to 11 m 1.2 m 1.2 m 1.2 m 3.0 m
Above 11 m and up to 14.5 m 1.5 m 1.5 m 2.5 m 4.0 m

NKDA’s figures for plots up to 3 cottah are mostly smaller: 0.75 m at the front, 3.0 m at the rear, 0.9 m on side 1 and 1.2 m on side 2. Setbacks eat into a narrow plot. On a plot 16 ft wide, two side setbacks of 1.2 m (about 4 ft each) leave about 8 ft for the building, which is why narrow-front houses are planned around a stair, a light well and a long thin plan. The post on courtyard house design for hot and humid climates covers that planning logic.

What can I build on 2, 3 and 5 cottah in practice?

The table gives a ceiling in each case: the footprint at the coverage limit multiplied by the number of floors. It is not a design. Stairs, lift, setbacks, plot shape and structure reduce it, and for a plot where a floor area ratio applies the FAR can cap it.

Visualisation of the double-height living room in the Ballygunge Place house
Visualisation of the Ballygunge Place house, planned on a plot of 1,441 sq ft (about 2 cottah) with 2,665 sq ft of built-up area over three floors. The house is not yet built. Visualisation: Residence, Ballygunge Place, Kolkata, by the studio.
Plot G+2 (3 floors) G+3 (4 floors) Road needed under the 2007 rules
2 cottah about 2,800 sq ft about 3,700 sq ft Above 3.5 m for G+2; above 7 m for G+3
3 cottah about 4,200 sq ft about 5,600 sq ft Above 3.5 m for G+2; above 7 m for G+3
5 cottah about 6,300 sq ft about 8,400 sq ft Above 3.5 m for G+2; above 7 m for G+3

For the 2007 rules, the FAR table in rule 53 begins above 14.5 m, so coverage and height are the main limits on a G+2 or G+3 house in a municipality. In New Town, Table IV caps a residential plot below 1,500 sq m at an FAR of 2.5, which is about 5,400 sq ft on a 3 cottah plot, so G+3 at full coverage (about 5,600 sq ft) would slightly exceed it.

Two of the studio’s designs show how small plots are stacked. The Ballygunge Place residence has 2,665 sq ft of built-up area over three floors on a 1,441 sq ft plot, which is an FAR of about 1.85, and rises to 30 ft. See the project page. Dream Villa has 1,918 sq ft over ground and three floors at 41 ft on its 1,138 sq ft plot, about 480 sq ft a floor. See the project page. The Ballygunge Place house is in visualisation and Dream Villa is complete. Neither figure is a rule.

What does a 1.5 katha house look like in West Bengal?

A 1.5 katha plot is about 1,080 sq ft. At 65% coverage the footprint is about 700 sq ft, and a G+2 house reaches about 2,100 sq ft in total before setbacks and stairs. The lane width decides whether G+2 is allowed at all, and the front setback of 1.2 m on a plot this small is a large share of the depth.

Does a small plot qualify for a faster KMC sanction?

Possibly. Construction World reported in December 2023 that KMC would let owners of plots up to seven cottahs get approval through an architect or Licensed Building Surveyor, with the plan treated as sanctioned once the fee is paid. Other reports have given other limits. The post on KMC building plan sanction lays out the sources and where they differ.

What to do next

Start with three facts about the plot: its area in the deed, the width of the road in front and the authority it falls under. With those, an architect can tell you how many floors the rules allow before any drawing is made. The studio’s architecture and building plan approval pages describe how it works, and you can send the plot details through the contact page.

Questions people ask

How many square feet is 1 cottah in Kolkata?

One cottah is about 720 sq ft, or about 66.9 sq m. A katha in West Bengal is the same unit, so 1.5 katha is about 1,080 sq ft and 3 cottah is about 2,160 sq ft.

How many floors can I build on a 3 cottah plot in Kolkata?

It depends on the road in front and the authority. In a West Bengal municipality, a road above 3.5 m wide allows 11 m height and a road above 7 m allows 14.5 m, which is about G+2 and G+3. KMC and NKDA have their own tables.

What is the ground coverage for a 3 cottah plot?

The WB Municipal (Building) Rules, 2007 allow 65% ground coverage for plots up to 200 sq m, and NKDA allows 65% for residential plots up to 3 cottah or 200 sq m. A 3 cottah plot is about 200.7 sq m, so the figure is about 65%.

What are the setbacks for a G+2 house in West Bengal?

For a residential building above 8 m and up to 11 m in a municipality, the 2007 rules set 1.2 m at the front and on side 1 and side 2, and 3.0 m at the rear. NKDA sets 0.75 m, 0.9 m, 1.2 m and 3.0 m for plots up to 3 cottah.

What can I build on a 1.5 katha plot in West Bengal?

A 1.5 katha plot is about 1,080 sq ft. At 65% coverage the footprint is about 700 sq ft, so a G+2 house comes to about 2,100 sq ft in total, before stairs and setback geometry reduce it.

Is G+3 possible on 2 cottah in Kolkata?

Only if the authority's height, road width and open-space rules allow it. Under the 2007 municipal rules, G+3 is about 12 m, which needs a road wider than 7 m, so a narrow lane usually caps a 2 cottah house at G+2.

Work by the studio mentioned here

Sources

  1. The West Bengal Municipal (Building) Rules, 2007, Government of West Bengal (Kolkata Gazette, 14 February 2007). Accessed 2026-11-13.
  2. New Town Kolkata Development Authority Act, 2007 and Building Rules, 2009 (compiled), New Town Kolkata Development Authority. Accessed 2026-11-13.
  3. KMC streamlines home construction process for small plot owners, Construction World (7 December 2023). Accessed 2026-11-13.

Rules, fees and costs change. Figures are as published on the dates shown; check the current circular with the authority before you rely on them. This page is general information, not legal or financial advice.

Read next

  • KMC building plan sanction in Kolkata: online steps, documents, timeline

    A plot owner in Kolkata engages a KMC-empanelled architect or Licensed Building Surveyor, who files the plan online under the KMC Act, 1980 and the KMC Building Rules, 2009. Reported timelines range from 15 to 30 days for the fast track and 45 to 90 days from one vendor.

    Guides,
  • Completion and occupancy certificate in Kolkata: who issues it and how

    In Kolkata Municipal Corporation limits the permission to occupy is called the Completion Certificate. Other West Bengal municipalities and NKDA call it the Occupancy Certificate. Each needs a notice within one month of completion, an inspection within 15 days, and a structural stability certificate signed by the engineer.

    Guides,
  • FAR and setback rules in Kolkata: what you can build on your plot

    Under the KMC Building Rules, 2009 the FAR for a residential plot in Kolkata depends on the width of the road in front: 1.25 on a road of 2.4 to 3.5 m, 1.75 on 3.5 to 7 m, 2.25 on 9 to 15 m. Ground coverage is 60 per cent up to 200 sq m, and the height and setbacks also follow the road width and height.

    Guides,
  • House elevation design: front elevation, G+2 and facade materials

    An elevation is a flat drawing of one face of a building, and the front elevation is the street face of a house. In Kolkata the facade also has to shed rain, shade the rooms and limit heat gain, so deep slab edges, screens and a brick base matter as much as the look. A G+2 house has ground plus two floors.