Mrinalini
Architects
মৃণালিনী
  1. Home
  2. Blog
  3. Guides

NKDA building plan approval in New Town: rules, documents, steps

Indo-Saracenic style front of the New Town banquet hall with ornate gates
The banquet hall at New Town, shown with its Indo-Saracenic front. The building is under construction. Photograph: Banquet hall, New Town, Kolkata, by the studio.

The short answer

In New Town, the plan is sanctioned by NKDA under its Building Rules, 2009, applied for online through OBPAS by an enlisted architect and engineer. The rules allow 60 days from a complete application, 65% ground coverage on plots up to 3 cottah, and a maximum FAR of 2.5 for residential plots below 1,500 sq m.

NKDA building plan approval is sanction from the New Town Kolkata Development Authority under its Building Rules, 2009. An enlisted architect and engineer apply online through OBPAS. The Rules allow 60 days from a complete application. For residential plots up to 3 cottah, ground coverage can reach 65%.

What are the NKDA building rules?

The New Town Kolkata Development Authority (NKDA) plans and regulates building in New Town, Rajarhat. Building plans there follow the New Town Kolkata Development Authority Act, 2007 and the Building Rules, 2009. NKDA publishes both as a compiled document, which this post reads, accessed on 13 November 2026. Rules are amended from time to time, and NKDA’s circulars carry later changes, so confirm current figures before you design.

Two terms in the Rules matter for every plot:

  • Ground coverage is the area of the plot covered by the building at ground level, divided by the total plot area, as a percentage.
  • Floor area ratio (FAR) is the total covered area on all floors, excluding the areas the Rules exempt, divided by the plot area.

How do I apply for NKDA plan sanction online?

Application is online only. NKDA’s building department FAQ says a plot owner must engage a registered architect and an enlisted engineer, who prepare the plan, structural design and soil test under the 2009 Rules, and that hard-copy submission is not accepted: you apply through OBPAS.

  1. Confirm the plot. Check the deed, the mutation record and the plot’s use and road width, because height and open spaces depend on the road.
  2. Appoint enlisted technical persons. NKDA publishes a list of enrolled technical persons. Section 36A of the Act requires professionals working in New Town to hold a certificate of enlistment, renewed annually.
  3. Prepare drawings and reports. Architectural, structural and service drawings, with a soil report where the building is tall enough to need one.
  4. Upload on OBPAS. The professionals submit the application with digitally signed declarations.
  5. Respond to queries and pay the sanction fee. The sanction is issued once the application is complete and the fee is paid.
  6. Send the commencement notice. Before work starts, a notice under rule 12(1), Schedule IV, goes to NKDA.

The Rules require the notice at least seven days before work begins, and one set of approved drawings must be kept at the site until the occupancy certificate is issued (rule 12).

What documents does NKDA ask for?

NKDA’s list of documents for a complete application has 17 items. The main ones are in the table below.

Document Condition
Registered deed of conveyance with site plan All applications
Memorandum of possession All applications
Mutation certificate (Form G) or record of title All applications
Up-to-date property tax All applications
Digitally signed declarations of architect and civil or structural engineer All applications
Geotechnical declaration and soil test report Buildings 15.1 m high or more
NOC from West Bengal Fire and Emergency Services Residential above 15.1 m, or any non-residential building
NOC from the Airport Authority of India Residential above 15.1 m if not in the height clearance list, or any non-residential building
Solar energy declaration Buildings above 15.5 m
Town planner or urban designer declaration Plots above 2 hectares
Plantation plan approved by Forest Department Built-up area above 20,000 sq m

The FAQ adds that a pollution control board clearance is needed above 150,000 sq m of built-up area and that the fire safety recommendation also applies to any plot above 1,500 sq m. The boundary wall needs sanction as well. The FAQ gives 1.5 m of masonry from ground level, or 900 mm with wire mesh above, and a solid portion of at most 750 mm at splayed corners.

What are the ground coverage and FAR in New Town?

They depend on plot size and use. Table IV of the Rules gives these maximums.

Plot size Residential, educational, institutional: FAR Ground coverage Business, assembly: FAR Ground coverage
Below 1,500 sq m 2.5 55% 2.0 45%
4,000 sq m 2.35 50% 2.0 40%
2 hectares 2.25 45% 2.0 40%

Small residential plots get more. Sub-rule (7)A of rule 22 sets, for residential plots up to 3 cottah or 200 sq m, a maximum ground coverage of 65% and these minimum open spaces:

Open space Minimum
Front 0.75 m
Rear 3.0 m
Side 1 0.9 m
Side 2 1.2 m

The Rules add incremental FAR in set cases. Green buildings rated IGBC Gold or GRIHA four star can claim 10% more. Mass housing, hospitals, IT buildings and mega commercial projects can claim 15% more where infrastructure allows, and strips near the metro corridor can claim 15% to 20%. Height is tied to the access road. Table III gives a maximum of 15.1 m where the road is up to 10 m wide.

For what 3 cottah and 5 cottah can hold, see the post on house plans for 2, 3 and 5 cottah plots in Kolkata.

How long does NKDA take, and how long is the sanction valid?

Rule 10 says that within 60 days of receiving an application completed in all respects, the Sanctioning Authority shall accord sanction or reject the application. A rejection does not stop the owner from applying again.

Under rule 11, a sanction is valid for five years and can be renewed for another five on payment of 15% of the building sanction fee. A complete application is the key to speed, since the 60 days run only from the date the file is complete.

How do I get an NKDA occupancy certificate?

The architect and engineer who signed the commencement notice apply on OBPAS. NKDA’s list of documents for an occupancy certificate for small projects (up to G+4) includes:

  1. The Schedule VII notice of completion.
  2. The completion plan with all revisions, and the structural drawings.
  3. Structural stability certificates for the building and the underground reservoir.
  4. Completion certificates for plumbing and drainage, and for electrical work.
  5. A lift certificate, where there is a lift.
  6. The approved service drawings, the mutation certificate, the FAR calculation sheet and car parking statement, and the sanction letter.

Under rule 14, NKDA inspects within 15 days of receiving the completion notice and issues the certificate within one month of the inspection. Bulk projects add a fire safety certificate and a certificate for the transformer and sub-station.

What is the construction site discipline NKDA expects?

The FAQ also covers site conduct. Building material may be stacked on a footpath for six months from commencement, leaving 1.5 m for pedestrians. After that it must stay within the plot, and a fine of ₹50,000 may be charged for breaches. Debris has to be taken to a designated place at the owner’s cost, or NKDA will remove it at ₹2,000 a tonne if informed in advance.

New Town banquet hall facade under construction, with FRP panels and scaffolding
The facade on site, with FRP panels fixed behind scaffolding. On site: Banquet hall, New Town, Kolkata, by the studio.

How does a non-residential building in New Town differ?

A hall, hotel or office faces more clearances than a house. The studio’s banquet hall in New Town stands on a site of 61,569 sq ft (about 5,720 sq m) and is under construction. For a non-residential building like it, NKDA’s document list requires the fire NOC and the Airport Authority NOC whatever the height. If a hall of that size falls in the business and assembly column of Table IV, the Rules give a maximum FAR of 2.0 and ground coverage of 40%, subject to the sanction.

Long-span steel roof trusses over the New Town hall during construction
On site at New Town: the long-span steel roof of the hall, a large assembly building that carries more clearances than a house. On site: Banquet hall, New Town, Kolkata, by the studio.

The roof design for a column-free hall is covered in the post on column-free banquet halls, and the fire and licence approvals for such halls in the post on banquet hall design and fire NOC.

What to do next

The studio is empanelled with NKDA and prepares sanction drawings in-house. If you hold a plot in New Town, send the plot number, area and intended use through the contact page. The building plan approval service page lists what the studio prepares for the authority, and the post on KMC building plan sanction covers the corporation’s process for the rest of the city.

Questions people ask

How do I get building plan approval from NKDA in New Town?

Engage a registered architect and an enlisted engineer, who prepare the plan, structural design and soil test under the NKDA Building Rules, 2009. They apply through OBPAS, because NKDA does not accept hard-copy applications.

What is the ground coverage in New Town Kolkata?

For residential plots up to 3 cottah or 200 sq m, the maximum ground coverage is 65%. Table IV of the Rules gives 55% for residential plots below 1,500 sq m, 50% at 4,000 sq m and 45% at 2 hectares.

What is the FAR in New Town for a residential plot?

Table IV of the NKDA Building Rules, 2009 gives a maximum FAR of 2.5 for residential, educational and institutional plots below 1,500 sq m, 2.35 at 4,000 sq m and 2.25 at 2 hectares. Extra FAR is available in set cases.

How long does NKDA take to sanction a building plan?

Rule 10 of the Rules says the Sanctioning Authority shall accord or reject sanction within 60 days from receiving an application completed in all respects. The online service may state its own limit, so check the portal.

Do I need a fire NOC for a building in New Town?

NKDA's guidance says a fire safety recommendation from the West Bengal Fire and Emergency Services is mandatory for all non-residential buildings, and for any building taller than 15.1 m or on a plot above 1,500 sq m.

How do I get an occupancy certificate in New Town?

The architect and engineer who signed the commencement notice apply on OBPAS with the completion notice, completion plan and certificates. Under rule 14, NKDA inspects within 15 days and issues the certificate within a month of the inspection.

Work by the studio mentioned here

Sources

  1. Building Department, frequently asked questions, New Town Kolkata Development Authority. Accessed 2026-11-13.
  2. Documents required for building plan sanction, New Town Kolkata Development Authority. Accessed 2026-11-13.
  3. List of required documents for OC/POC, New Town Kolkata Development Authority. Accessed 2026-11-13.
  4. New Town Kolkata Development Authority Act, 2007 and Building Rules, 2009 (compiled), New Town Kolkata Development Authority. Accessed 2026-11-13.

Rules, fees and costs change. Figures are as published on the dates shown; check the current circular with the authority before you rely on them. This page is general information, not legal or financial advice.

Read next

  • Completion and occupancy certificate in Kolkata: who issues it and how

    In Kolkata Municipal Corporation limits the permission to occupy is called the Completion Certificate. Other West Bengal municipalities and NKDA call it the Occupancy Certificate. Each needs a notice within one month of completion, an inspection within 15 days, and a structural stability certificate signed by the engineer.

    Guides,
  • Building a house in Kolkata while living abroad: POA, approvals, payments

    An NRI or OCI may buy non-agricultural property in India under RBI's Master Direction, and may be represented by an attorney under a power of attorney executed before a notary, magistrate or Indian consul and then stamped in West Bengal. Building authorities accept an authorised representative as applicant. Pay by stage against measured work.

    Guides,
  • Banquet hall design: layout, exits and fire NOC in West Bengal

    A banquet hall in West Bengal is an assembly building under NBC 2016, Group D. It needs a fire NOC at any height, exit doors at least 2.0 m wide, a travel distance of 30 m to an exit (45 m if fully sprinklered) and exit width sized from the number of guests. Plan the exits and the fire clearance before the facade.

    Public and commercial,
  • Commercial building design in India: approvals, fire NOC, cost drivers

    A commercial building in West Bengal needs a sanctioned plan from the municipality and a fire NOC at any height. NBC 2016 sets at least two exits on every office floor, a 30 m travel distance and occupant loads of 10 sq m per person for offices. Plot size, height, lifts and fire systems drive cost more than finishes.

    Public and commercial,

All articlesMore in guides