Smart home wiring in new construction in India: what to run before plaster

Visualisation of the living room in the Skydale Tower duplex in Siliguri
The living room of the Skydale Tower duplex, in visualisation. The project is ongoing. Visualisation: Skydale Tower duplex, Siliguri, West Bengal, by the studio.

The short answer

Smart devices are easy to add later only if the conduits, power points and neutral wires are already in the wall. IS 732 caps conduit fill at 40 per cent, allows no more than four quarter bends between outlets, and asks for a 30 mA RCD on socket circuits where earthing is not effective.

Smart devices are easy to add later only if the conduits, power points and neutral wires are already in the wall. IS 732 caps conduit fill at 40 per cent and allows no more than four quarter bends between outlets, and it asks for a 30 mA RCD on socket circuits where earthing is not effective.

Why wire a smart home at construction stage?

A wall that is plastered cannot be opened cheaply. The cables that a smart home needs are few, and they are best laid when the walls are bare: spare conduit, a neutral at every switch, a data path to a central point and a provision at the parking. The devices themselves change fast, and conduit does not. The studio’s interiors, such as the Skydale Tower duplex in Siliguri, are resolved down to furniture and lighting, and the same planning applies to what is behind the wall.

The items below are practice, not code, unless a standard is named. The code text read here is IS 732 of 1989 and the 2005 National Building Code. Later editions exist, so ask the electrician which one he follows.

What do the standards say about conduit?

IS 732:1989, Appendix B, gives these limits for conduit in a household installation:

Rule Figure
Space factor, the share of the conduit filled by cable Not more than 40 per cent
Inspection box, minimum size 75 x 75 mm
Quarter bends between outlets Not more than four
ac and dc conductors In separate conduits

NBC 2005, Part 8 Section 2, says telephone wiring in multi-storey housing is generally done in concealed conduits, and that telecom needs should be planned well in advance. A fill limit of 40 per cent is the reason to choose a conduit one size larger than today’s cable needs, so that a second cable can be pulled later.

How should power circuits be planned?

Give each heavy appliance its own circuit. NBC 2005 says each 16 A socket for an air conditioner or water cooler gets its own fuse or MCB, and that inverter and UPS circuits need MCB, MCCB or ELCB protection on both the incoming and the outgoing sides. The code’s guide schedule for sockets is two to three five-amp and one fifteen-amp in a bedroom, and two to three five-amp and two fifteen-amp in a living room. Sockets go at least 20 cm above the floor, and the controlling switch is on the live side of the line.

Visualisation of the kitchen in the Skydale Tower duplex
A kitchen in the Skydale duplex, in visualisation. Kitchens carry the heaviest appliance load, each on its own circuit. Visualisation: Skydale Tower duplex, Siliguri, West Bengal, by the studio.

For protection, IS 732:1989 says every socket outlet circuit in a household installation on a TT system, or where earthing is not effective, shall be protected by a residual current device with a rated residual operating current not exceeding 30 mA. The RCD has to be able to disconnect all the phase conductors of the circuit. Secondary guides say IS 732 was revised in 2019 to align with IEC 60364, and that edition was not read for this post, so confirm the current requirement.

What do you run for lighting and switches?

Run a neutral wire to every switch box, and a spare conduit from each switch point to the ceiling. Commercial guides say many smart switches need a neutral and that older Indian boxes often have none. This does not come from a BIS text, so read the installation sheet of the product you want. A neutral at each box costs little at wiring stage and a great deal to add later.

Backlit onyx panel in the Muchipara studio apartment
The backlit onyx panel in the 457 sq ft Muchipara studio. Lighting like this needs its power and control cable planned inside the wall. Photograph: Studio apartment, Muchipara, Kolkata, by the studio.

Plan lighting by scene, not by point. The studio’s 457 sq ft Muchipara studio uses a backlit onyx panel as the single point of light and focus in the room. A feature like this wants its own circuit and a place for a dimmer or driver that can be reached for service. See the guide to the small studio apartment interior.

What about data, Wi-Fi and security?

Put a central cabinet in a ventilated, accessible place, and run data conduit from it to each room that will have a desk, a television or an access point. NBC 2005 defines computer networking only as linking computing devices and gives no cable grade, so no Indian code figure for residential data cabling was found. Ask the installer to name the cable category and the standard it follows.

ENS 2024 Annexure 6 covers smart homes as a recommendation. It says connected devices must have reasonable security features and follow common interoperability standards. It cites a Connected Device Alliance estimate of 20 to 30 per cent household energy savings. Treat it as the code’s citation of that body’s estimate, not as a measured result for your home.

How do you provide for EV charging?

Run a conduit from the distribution board to each parking space, even if no charger is planned. The Ministry of Power’s guidelines of 17 September 2024 say residents can install private EV charging stations in their designated parking spaces, with supply from the existing meter or a sub-meter. They note that the Ministry of Housing and Urban Affairs amended the Model Building Bye-Laws 2016 and urge local bodies to allocate charging space in new buildings. ENS 2024 clause 5.2.2.3 says any EV charging infrastructure on the premises must follow those guidelines, and clause 5.2.2.4 asks for power cabling sized so that distribution losses are at most 3 per cent.

The guide to apartment building design on a Kolkata plot covers parking rules, and any building-level charging requirement is set by the local body.

A checklist for the electrician

Give the electrician a list before wiring starts:

  1. A neutral at every switch box.
  2. Conduit one size larger than the cable, with draw wires, and inspection boxes of at least 75 x 75 mm.
  3. Separate circuits for each air conditioner, the kitchen appliances and the water heater.
  4. An RCD on socket circuits, with the rating confirmed against the current IS 732.
  5. A data conduit from a central cabinet to each room.
  6. A spare conduit to each ceiling and each parking space.
  7. A drawing of every conduit run, photographed before plastering.

The site supervision checklist shows where to inspect services before they are covered.

What next?

Decide the wiring list at the interior design stage, because the furniture and lighting decide where the points go. The studio’s interior design service and architecture service cover this planning, and the contact page is the way to begin.

Questions people ask

What should I wire into a new house for a smart home?

Run spare conduit with draw wires to ceiling and switch points, a neutral wire to every switch box, a data conduit to a central cabinet, and a provision for EV charging at the parking. Fit devices later, when the choice of brand is clearer.

Do smart switches need a neutral wire?

Commercial guides say many models do, and that older Indian switch boxes often lack one. No BIS or NBC text on this was found, so read the installation sheet of the product you plan to buy, and run a neutral to each box if in doubt.

Is an RCD required in a house in India?

IS 732 of 1989 asks for a residual current device with a rating of not more than 30 mA on every socket outlet circuit in a household installation on a TT system or where earthing is not effective. The standard has been revised since, so confirm the current edition with your electrician.

How full can a conduit be?

IS 732:1989 sets a space factor of not more than 40 per cent, a minimum inspection box of 75 x 75 mm, and not more than four quarter bends between outlets. It asks for ac and dc conductors in separate conduits.

How do I provide for EV charging in a new building?

The Ministry of Power guidelines of 17 September 2024 say residents can install private charging stations in their designated parking spaces, with supply from the existing meter or a sub-meter. ENS 2024 says any EV charging infrastructure must follow those guidelines. Run a conduit to the parking space.

Work by the studio mentioned here

Sources

  1. IS 732: 1989, Code of practice for electrical wiring installations, Bureau of Indian Standards (public copy). Accessed 2026-11-13.
  2. National Building Code of India 2005, Part 8 Section 2, Electrical installations (SP 7), Bureau of Indian Standards (public copy). Accessed 2026-11-13.
  3. Eco-Niwas Samhita 2024, clause 5.2.2 and Annexure 6, Bureau of Energy Efficiency, Ministry of Power. Accessed 2026-11-13.
  4. Guidelines for installation and operation of electric vehicle charging infrastructure, 2024, Ministry of Power, Government of India. Accessed 2026-11-13.

Rules, fees and costs change. Figures are as published on the dates shown; check the current circular with the authority before you rely on them. This page is general information, not legal or financial advice.

Read next

  • Modular kitchen design for Indian homes: layouts, materials and exhaust

    A modular kitchen is built from factory-made cabinet units fitted to the room. In Kolkata the sanction rules set the room: KMC asks for at least 4.5 sq m, 1.5 m wide, with a window of 1 sq m or more. Choose boiling-water-resistant plywood, not plain MDF, for the sink and hob units, and plan the exhaust at the sketch stage.

    Design and styles,
  • Interior design trends 2026 in India: what works in Kolkata flats

    The 2026 trends in Indian interiors are soft, warm whites led by Pantone's Cloud Dancer, Japandi and minimalism, and compact homes planned with built-in storage. In Kolkata, where mean humidity is about 69% and peaks near 83% in August, wood, cane and plywood need sealed finishes and dry detailing to last.

    Trends,
  • 3D visualisation in architecture: what a render shows and what it hides

    A 3D visualisation shows proportion, massing, sightlines, colour and the way rooms connect before anything is built. It does not show heat, sound, cost, structure or how materials age. Research on design review also warns that a photorealistic render can make a design look more finished than it is.

    Trends,
  • AI in architecture for Indian clients: what changes and what does not

    AI tools can produce pictures and design options quickly. They do not know your plot, the sanction rules or the structure, and no Indian rule found makes an AI tool responsible for a drawing. Under the Architects Act 1972 and the CoA conduct regulations, the registered architect answers for the work.

    Trends,

All articlesMore in trends